Projects

Western Turner Syncline

Western Turner Syncline

  • Client: Monadelphous
  • Project Timeframe: April 2013- March 2014
  • Location: Tom Price Mine, Pilbara Region, WA
  • Contract Value: $22 million

The design and construction of the 33kV distribution infrastructure to serve the WTS Section 10 primary crushing, overland conveying and stockpiling facilities.

Mungullah Power Station Carnarvon

Mungullah Power Station Carnarvon

  • Client: Horizon Power
  • Project Timeframe: Feb 2013- May 2014
  • Location: Carnarvon, Western Australia
  • Contract Value: $10 million

Contraflow was engaged to complete a Balance of Plant agreement for works at the Mungullah Power Station in Carnarvon, owned and operated by Horizon Power.

Wickham Underground Cable Replacement

Wickham Underground Cable Replacement

  • Client: Rio Tinto Iron Ore
  • Project Timeframe: June 2011- April 2013
  • Location: Town of Wickham, Karratha
  • Contract Value: $6 million

Decommissioning and replacement of the existing 415V consac cables and service pillars in the town of Wickham

City of Rockingham Traffic Management

City of Rockingham Traffic Management

  • Client: City of Rockingham
  • Project Timeframe: 2011-2013
  • Location: City of Rockingham
  • Contract Value: $700,000 per annum

An ongoing contract to supply the City of Rockingham with Traffic Management Services

Programmed Facility Management

Programmed Facility Management

  • Client: Programmed Facility Managment
  • Project Timeframe: 2009 - ongoing
  • Location: Throughout the metropolitan area
  • Contract Value: 1.8 million per annum

Programmed Facility Management and Contraflow have engaged in an ongoing contract for the supply of Traffic Management Services in the Perth Metropolitian Area.

Western Power Traffic Management Contract

Western Power Traffic Management Contract

  • Client: Western Power
  • Project Timeframe: 2005 - ongoing
  • Location: Throughout the metropolitan area
  • Contract Value: 1.5 - 2 million per annum

Western Power has engaged in a 3 year contract with Contraflow to provide traffic management services relating to Western Power's works throughout the Perth Metropolitan Area.

Future Grid Traffic Management

Future Grid Traffic Management

  • Client: Future Grid
  • Project Timeframe: Nov 2011 - Nov 2013
  • Location: Perth Metropolitan & Surrounds
  • Contract Value: approx $1.8m per annum

Supply of traffic managment services relating to Future Grid's service works on network assets. 

Lancelin Wind Farm

Lancelin Wind Farm

  • Client: Blair Fox
  • Project Timeframe: May 2012 – Aug 2012
  • Location: Lancelin WA
  • Contract Value: $3.5 million

 Supply, installation, testing, commissioning and certification of high voltage distribution for two wind farms in the Lancelin area.

Chichester Power Distribution Network Expansion

Chichester Power Distribution Network Expansion

  • Client: Fortescue Metals Group
  • Project Timeframe: Mar 2012 – Aug 2012
  • Location: Christmas Creek, Chichester Range WA
  • Contract Value: $8.8 million

Design, supply, fabrication, transportation, site installation, testing, commissioning and close-out for the expansion of the Christmas Creek Chichester Power Network. 

Chichester Civil Works

Chichester Civil Works

  • Client: Fortescue Metals Group
  • Project Timeframe: Mar 2012 – Aug 2012
  • Location: Christmas Creek, Chichester Range WA
  • Contract Value: $8.8 million

Associated civil works in conjunction with the power network expansion at Christmas Creek Mine Site.